Flexible-circuit standards in sourcing

IPC-2223F vs IPC-6013F for FPC Membrane Switch RFQs

IPC-2223F and IPC-6013F have different jobs in an FPC membrane-switch RFQ. IPC-2223F is the sectional design standard for flexible and rigid-flexible printed boards; IPC-6013F is the qualification and performance specification. Name the applicable document, revision, construction and acceptance evidence instead of writing only “IPC compliant.” Confirm first that the quoted circuit is a flexible printed board, not a printed-silver film circuit.

Executive answer

Resolve three questions before naming an IPC document

  • IPC-2223F addresses flexible-board design, while IPC-6013F addresses qualification and performance; one reference cannot silently substitute for the other.
  • Confirm the actual circuit platform before citing either document because “membrane switch” describes the interface assembly, not one universal circuit construction.
  • Make every standards reference quotable by recording the revision, applicable project selections, deviations, specimen, method, acceptance criteria and evidence owner.

Current guidance context

Two current documents, two different procurement questions

The Global Electronics Association’s current status page lists IPC-2223F, Sectional Design Standard for Flexible/Rigid-Flexible Printed Boards, as published in May 2026 and IPC-6013F, Qualification and Performance Specification for Flexible/Rigid-Flexible Printed Boards, as published in June 2026. The publication timing makes the revision letters worth checking in any new RFQ, but the titles are more important than their proximity: one is a design document and the other is a qualification and performance document.

A useful RFQ therefore does not ask whether an FPC membrane switch is simply “IPC compliant.” It identifies the circuit platform, assigns each standard to a defined deliverable and states the evidence the buyer expects. That record prevents a design citation, a fabrication claim and a finished-interface approval from being treated as the same promise.

Global Electronics Association status of standardizationHYR FPC membrane-switch product scope
01

Confirm the circuit platform before citing a board standard

An FPC membrane switch normally refers to a user interface integrated with a flexible printed board, commonly a copper circuit on polyimide. A conventional membrane switch may instead use screen-printed conductive ink on polyester. Both can route key contacts to an equipment controller, but their materials, fabrication data and evidence paths are not interchangeable.

Start the RFQ with a circuit-platform declaration. Name the substrate and conductor system, the intended layer construction and the boundary between the fabricated circuit and the overlay, spacer, adhesive, domes, LEDs, connector and other assembled parts. If the supplier is expected to propose the platform, require the proposal to identify it explicitly and explain which standards references apply to that proposed construction.

Do not let a product-family name become a conformity claim. The presence of an FPC-style tail, a fine-pitch connector or a flexible shape does not by itself prove that a circuit was designed, qualified or accepted to a named IPC document. The released fabrication package and agreed records must carry that meaning.

Compare printed-film, FPC and PCB design routes
02

Assign IPC-2223F to the design basis

IPC-2223F is identified by the standards body as the sectional design standard for flexible and rigid-flexible printed boards. In an RFQ, that makes it a candidate reference for the controlled design basis when the actual circuit platform and contract make it applicable. The Global Electronics Association’s design-suite page also places IPC-2223 within the family of printed-board design standards rather than presenting it as a finished-product certificate.

A design reference needs project inputs. Release the schematic or net list, outline and stack assumptions, supported and flexible regions, installed bend condition, conductor and pad interfaces, component and stiffener boundaries, tail geometry and connector definition. Record who owns each input and which drawing revision the supplier is quoting.

The citation should also expose open decisions. If a construction type, use condition or other project selection has not yet been agreed, mark it as open instead of allowing each supplier to choose silently. Obtain the current purchased standard and qualified engineering review for detailed requirements; a public title or this article is not a substitute for the document.

Official IPC design standards suiteHYR controlled drawing checklist
03

Assign IPC-6013F to qualification and performance evidence

IPC-6013F is listed as the qualification and performance specification for flexible and rigid-flexible printed boards. A buyer citing it should define what evidence is required for the project rather than assume that the document title creates a universal certificate. State the exact revision and the project-selected construction, classification or acceptance basis that the responsible parties determine from the purchased document.

Then identify the specimen and record. Separate any initial qualification evidence from lot or delivery acceptance, and name the characteristics, methods, sample basis and acceptance criteria required by the contract. Ask the fabricator or assembly supplier to identify exclusions, deviations and subcontracted evidence before price comparison, not after a sample is built.

Keep evidence attached to the product state it represents. A fabricated flexible-board record does not automatically approve mounted domes, printed overlay alignment, LEDs, adhesive bonding, connector mating or the behavior of the completed equipment. Those interfaces need their own controlled observations.

Verify the current IPC-6013 revision and title
04

Build a document-role matrix that suppliers can quote

Put the standards schedule beside the drawing list. For each cited document, record the revision, the deliverable it controls, any buyer-selected class or type, approved deviations, evidence format and owner. This turns a broad compliance phrase into fields that can be confirmed, priced or challenged.

The matrix below is an original editorial worksheet, not a reproduction of either IPC document. Complete it with the current purchased standards and the actual contract. If a row is outside the supplier’s scope, identify the organization that retains it rather than leaving the evidence owner blank.

Use the same matrix during quotation review. Two prices are not comparable when one includes fabricated-board documentation and the other assumes customer acceptance from a functional sample alone. A declared evidence gap is a decision; an invisible gap becomes a dispute.

05

Separate board, membrane-switch and system approval

The fabricated FPC, the assembled membrane switch and the installed HMI are related but different evidence objects. Board fabrication records can address the controlled flexible-board state. Assembly checks can address component identity, circuit continuity, key operation, indicators, connector and visual workmanship within the agreed supply boundary. A mounted-interface review can address fit, tail routing, support, display alignment, access and interaction with the enclosure.

The equipment team still owns controller behavior, permitted states, electrical loading outside the supplied component, environmental exposure in the final machine and complete-product conformity. Record the exact sample, enclosure or fixture, drawing revision, method, result and approver for each review so evidence cannot be transferred to another configuration without analysis.

This separation also prevents overclaiming in supplier selection. A supplier may be able to quote an FPC construction and agreed records without claiming blanket certification of every membrane-switch assembly. Ask for the evidence that the project needs and evaluate it against the same controlled scope.

06

Release one FPC RFQ with explicit evidence ownership

Issue the same package to every candidate: circuit-platform declaration, schematic or net list, fabrication data, mechanical stack, bend and support map, tail and mating connector, component boundary, use environment, standards schedule, acceptance matrix, quantity basis and change-control expectations. Require each quotation to return assumptions and exclusions against those fields.

Before release, ask four questions. Is the circuit actually within the flexible or rigid-flexible printed-board scope being cited? Does the RFQ distinguish design requirements from qualification and performance evidence? Are the current revision and project selections controlled? Does every fabricated-board, assembled-component and mounted-system record have an owner? A “no” is a useful open item, not a reason to hide the uncertainty behind a general standards phrase.

For an HYR review, submit the current design package through the secure inquiry route and ask about the proposed circuit and supply boundary. HYR can review a project-specific FPC membrane-switch quotation; this page does not state that HYR or an unspecified product is certified to IPC-2223F or IPC-6013F.

Assemble the controlled RFQ packageSend an FPC package for HYR review

Decision matrix

Assign each RFQ field to its document and evidence owner

Original editorial document-role worksheet. Complete it from the current purchased standards and the actual project contract; it does not select applicability, class, type, test method or acceptance value.

Decision factorDesign and quotation recordQualification or acceptance recordBoundary to retain
Circuit platformDeclare substrate, conductor system, layers and supplied-assembly boundary before citing IPC-2223F.Confirm which fabricated construction and specimen the agreed IPC-6013F evidence represents.Do not transfer a flexible-board citation to a printed-silver film circuit or another construction by product name alone.
Design releaseControl the schematic, fabrication data, outline, stack, flex regions, tail, connector and applicable IPC-2223F selections.Record the exact released design revision associated with qualification or acceptance evidence.A design review is not a qualification result, and a passing specimen does not define an uncontrolled drawing.
Project classificationName the type, class, use condition or other selections only after the responsible parties determine them from the current documents.Apply the same controlled selections to specimens, methods, criteria and records where the contract requires them.Do not invent a class from the industry, equipment name or desired marketing position.
Fabricated FPC evidenceIdentify required fabrication outputs, deviations and change controls in the quotation package.Define qualification, lot or delivery records with specimen, method, sample basis, criteria and evidence owner.A general supplier capability statement is not the project record.
Membrane-switch assemblyDefine domes or printed contacts, overlay, spacer, adhesive, LEDs, connector, assembly boundary and functional map.Define continuity, key operation, visual, dimensional, connector and other agreed assembly observations separately.Flexible-board specifications do not by title approve every added material, component or assembly interface.
Mounted HMI and equipmentProvide enclosure support, routing, display, access and system-interface inputs needed by the component design.Approve fit and function on the identified mounted sample; retain controller, environment and complete-equipment evidence with their owners.A board or component record is not complete-machine conformity evidence.

Applicability and detailed requirements must be determined from the purchased current standards and the project contract by the responsible engineering and quality teams. No HYR conformance, certification, qualification result or customer approval is implied.

Before the RFQ

Frequently asked questions

Document role

Are IPC-2223F and IPC-6013F interchangeable in an FPC RFQ?

No. The standards body identifies IPC-2223F as a sectional design standard and IPC-6013F as a qualification and performance specification for flexible and rigid-flexible printed boards. A project may reference both for different controlled purposes, but applicability and detailed requirements must be determined from the current purchased documents and contract.

Circuit scope

Does every membrane switch fall under IPC-2223F or IPC-6013F?

No such blanket claim should be made. First identify whether the circuit is a flexible or rigid-flexible printed board, a printed-silver film circuit or another construction. Then the responsible engineering and quality teams determine which documents apply to the actual deliverable.

RFQ wording

Is “IPC compliant” enough for a supplier quotation?

It is too broad for a comparable quotation. Name the document and revision, the deliverable it controls, applicable project selections, deviations, specimen, method, acceptance criteria, evidence format and owner. Keep open decisions visible rather than allowing different suppliers to price different assumptions.

Approval boundary

Does an IPC-6013F board record approve the finished membrane-switch HMI?

Not by itself. The fabricated FPC, assembled membrane switch, mounted interface and complete equipment are different evidence objects. Define separate checks and owners for the added components, mechanical interfaces, controller behavior, environment and complete-product requirements.

A useful fit when

Who this guide helps

  • OEM engineers and buyers preparing an RFQ for a copper-on-polyimide FPC membrane-switch assembly.
  • Quality and sourcing teams comparing quotations that cite different IPC documents, revisions or evidence packages.

Limits to resolve

Scope and limitations

  • This guide does not reproduce the purchased standards, select a class or determine applicability for a particular design.
  • The standards-body titles and public scope pages do not establish HYR, supplier, product or customer compliance.
  • Printed-silver polyester membrane circuits and complete HMI assemblies need their own construction and acceptance definitions; they are not automatically covered by a flexible printed-board citation.

Prepare the RFQ

What to send for a useful review

  1. 01

    Circuit-platform declaration: substrate, conductor system, layer construction and the boundary between fabricated board and assembled membrane-switch parts.

  2. 02

    Controlled design package: schematic or net list, outline, stack, bend and supported regions, tail, connector, components and released revision.

  3. 03

    Standards schedule: exact document and revision, project-selected type or class where applicable, deviations, specimens, methods and acceptance criteria.

  4. 04

    Evidence matrix: design approval, fabricated-board records, assembly and functional checks, mounted-interface approval and responsible owner for each record.

Evidence boundary

Evidence and editorial method

The public Global Electronics Association status page lists IPC-2223F as the May 2026 sectional design standard and IPC-6013F as the June 2026 qualification and performance specification for flexible and rigid-flexible printed boards. Those titles support the document-role distinction only. HYR does not claim certification or conformance to either standard. The representative parent-company photograph shows assembly of printed membrane-switch layers and tails; it is not presented as a copper FPC, an IPC test specimen or a qualification result.

Publication approval: Owner-approved editorial publication; project-specific engineering approval is separate.

Technical reference basis

Sources and applicability

  1. IPC / Global Electronics AssociationStatus of Standardization
    Source date: IPC-2223F listed May 2026; IPC-6013F listed June 2026 · Accessed 9 September 2026

    Primary standards-body source for the current titles and publication months of IPC-2223F and IPC-6013F; the listing is not the standards text or evidence of HYR or product compliance.

  2. IPC / Global Electronics AssociationIPC Design Standards Suite
    Source date: Page publication date not stated · Accessed 9 September 2026

    Primary standards-body context placing IPC-2223 in the printed-board design suite; it does not determine project applicability, detailed requirements or acceptance evidence.

  3. IPC / Global Electronics AssociationIPC-2223E public table of contents
    Source date: Superseded Revision E published January 2020 · Accessed 9 September 2026

    Superseded January 2020 edition used only for public document-lineage and design-scope context; no Revision F requirement, project selection or conformance claim is drawn from it.

  4. IPC / Global Electronics AssociationIPC-6013D public table of contents
    Source date: Superseded Revision D published April 2017 · Accessed 9 September 2026

    Superseded April 2017 edition used only for public document-lineage and qualification/performance context; no Revision F requirement, test method or acceptance value is drawn from it.